Sequential Sheet Guide
Reference examples for proper PāF sequential sheet structure for fiber/conduit utility projects.
Core Rules & Conventions
P = Plan Sheet (Civil)
Shows the physical route ā trench, bore, conduit layout, manholes, stations, and depths. One P-sheet per segment.
F = Fiber Plan Sheet
Mirrors the exact P-sheet boundary. Shows fiber buffer tubes, splice assignments, and OTDR points. Same station range as its paired P.
Tombstone Must Match PāF
Both P and F sheets for the same segment must share identical Station From, Station To, footage, depth, and structure references (MH or HH numbers).
Exit Coords Copy to Next Entry
The Exit coordinates of sheet N become the Entry coordinates of sheet N+1, creating a seamless chain. The system auto-copies these when using PāF sync.
Pin Color = Completion Status
Pins are RED when sub-tasks remain open. They turn GREEN only when every sub-task checklist item is checked off. No sub-tasks = default fiber color.
Naming Convention
P sheets: C-1.0, C-2.0 ⦠F sheets: C-1.0F, C-2.0F ⦠Sequential order must be numerically consecutive for auto-detection to work.
Sheet Pairing Pattern
Every P-sheet (civil plan) is immediately followed by its paired F-sheet (fiber plan) covering the exact same station range.
Example Run
Main Trunk ā Station 0+00 to 12+50
Plan Sheet ā Sta. 0+00 to 4+00
Entry point from Vault MH-101. Route runs north along Oak Ave.
From
MH-101
To
MH-102
Footage
400 LF
Depth
42"
Bore required under Oak/Main intersection ā 80 LF HDD.
Fiber Plan ā Sta. 0+00 to 4+00
Mirrors P-1. Fiber colors, splice points, and buffer tube assignments shown.
From
MH-101
To
MH-102
Footage
400 LF
Depth
42"
Buffer tubes 1ā12 routed in this segment. Splice at MH-102.
Plan Sheet ā Sta. 4+00 to 8+25
Continues north. Manhole MH-102 at start. Crosses industrial access road.
From
MH-102
To
MH-103
Footage
425 LF
Depth
36"
Trench depth increases to 48" at road crossing per permit.
Fiber Plan ā Sta. 4+00 to 8+25
Mirrors P-2. Splice closure at MH-103 shown with buffer tube schedule.
From
MH-102
To
MH-103
Footage
425 LF
Depth
36"
Tube 1 continues. Tubes 2ā6 splice out at MH-103 for drops.
Plan Sheet ā Sta. 8+25 to 12+50
Final segment. Terminates at Vault MH-104 near substation.
From
MH-103
To
MH-104 (END)
Footage
425 LF
Depth
36"
Bore under creek per permit ā 120 LF HDD.
Fiber Plan ā Sta. 8+25 to 12+50
All 144 fibers terminate at MH-104. OTDR testing points marked.
From
MH-103
To
MH-104 (END)
Footage
425 LF
Depth
36"
All 12 tubes terminate. OTDR from MH-101 end-to-end required.
ā Run Complete ā What This Demonstrates
- 3 P-sheets + 3 paired F-sheets = 6 sequential sheets total
- Tombstone data (From/To/Footage/Depth) is identical on each PāF pair
- Exit coordinates of each sheet chain into the entry of the next
- Pins are š“ red on P-sheets (open tasks) and š¢ green on F-sheets (complete)
- Sheet numbers follow C-N.0 / C-N.0F naming for auto-detection